UAE infrastructure contractors pay 0% corporate tax on taxable income up to AED 375,000 and 9% above it under Article 3 of Federal Decree-Law No. 47 of 2022. Government road and utility contracts are taxed like any construction by stage of completion, performance bonds are deductible costs, and there is no tax exemption for public-sector work.
Basis: UAE Federal Tax Authority
- Corporate tax rates
- 0% on taxable income up to AED 375,000; 9% above
- Article 3, Federal Decree-Law No. 47 of 2022
- Government work
- No tax exemption for contractors on public-sector projects
- Federal Decree-Law No. 47 of 2022
- Mobilisation advances
- Liabilities until the work is performed
- Article 20, Federal Decree-Law No. 47 of 2022
- Small Business Relief
- Revenue up to AED 3,000,000; tax periods ending on or before 31 December 2029
- Article 21; Ministerial Decision No. 73 of 2023
# How corporate tax works for infrastructure contractors
Infrastructure contractors build roads, utilities and civil works, often for government clients: taxable income is certified revenue less earthworks, materials, plant and labour, taxed at the standard bands. The government customer changes nothing about the computation; there is no public-sector exemption for the contractor.
Programmes run for years with interim certifications, making stage-of-completion routine but critical. Dayworks and provisional sums are recognised as instructed and performed, with the rate schedules in the contract.
# Computing taxable income for infrastructure contractors
Borrow pits, quarries and batching plants operated for the project are part of project cost; their rehabilitation obligations may need provisions following the accounts. Heavy plant is capitalised and depreciated across the programme.
Construction businesses compute taxable income from accounting profit adjusted under Article 20 of Federal Decree-Law No. 47 of 2022, at the standard 0%/9% bands. Long-term contracts are recognised by stage of completion: revenue and margin follow certified progress, not cash received. Retention amounts are recognised when the right to them is established, usually at the defects period's end.
Variations and claims are recognised only when instructed or agreed, never on hope. Subcontractor costs, materials, labour and equipment hire are matched to the same progress, with year-end accruals for work done but not yet invoiced. Onerous contracts, where costs will exceed revenue, need provisions following the accounts.
Deductions that matter most for infrastructure contractors:
- Earthworks, materials and subcontractors are deductible matched to progress.
- Heavy plant is capitalised and depreciated; hired plant is deducted.
- Performance bonds, insurance and site establishment are deductible.
| Expense | Treatment |
|---|---|
| Materials and subcontractors | Deductible, matched to progress |
| Direct labour, visas, accommodation | Deductible |
| Equipment hire | Deductible as incurred |
| Owned plant and scaffolding | Capitalised; depreciated |
| Performance bonds and insurance | Deductible |
| Contractual delay penalties | Reduce revenue or deductible |
| Regulatory fines | Not deductible (Article 33) |
| Tender costs (win or lose) | Deductible business development |
# Government contracts: no exemption, extra paperwork
Government contracts bring stringent certification, audit and documentation regimes, which serve the tax computation well: certified quantities are the revenue evidence. They also bring performance deductions, liquidated damages and strict variation procedures, each with the standard tax treatment.
Advance mobilisation payments are liabilities until the work is performed. Retention follows the standard rule, recognised with certification. None of the government-specific mechanics creates a tax exemption; they create better records.
Construction's recurring errors are progress-shaped: recognising full contract value on signing, ignoring variations discipline, missing subcontractor accruals at the year-end, and treating retention as never receivable. Related-party plant hire and labour supply without benchmarking invite Article 34 adjustments, and cash-paid day labour with no records destroys the deduction evidence.
# Free zone vs mainland for infrastructure contractors
Construction work is performed where the project sits, which for UAE projects means mainland activity taxed at 9% regardless of where the contractor is licensed. A free zone contractor building in the mainland is a mainland taxpayer in substance on that work; construction is not a qualifying activity for the 0% rate.
Only genuinely separate free zone streams, such as design or project-management consultancy for other free zone persons, could be qualifying income. Keep contracting and consultancy segmented where both exist.
Infrastructure work in the UAE is mainland activity taxed at 9%; construction is not a qualifying activity for the 0% free zone rate.
# Worked example: infrastructure contractors tax computation
A contractor certifies AED 80 million on a roads programme: earthworks and materials AED 40 million, plant AED 12 million, labour AED 10 million, subcontractors AED 8 million and overheads AED 4 million:
Liquidated damages of AED 1 million for late sections would reduce revenue or be deductible, cutting tax by AED 90,000. The government client's audit of quantities doubles as the revenue evidence.
For help applying these rules to your own business, including registration, computations and filing, contact us for a quote.
| Item | Amount |
|---|---|
| Certified revenue | AED 80,000,000 |
| Less: earthworks and materials | (AED 40,000,000) |
| Less: plant (hire and depreciation) | (AED 12,000,000) |
| Less: labour | (AED 10,000,000) |
| Less: subcontractors | (AED 8,000,000) |
| Less: overheads | (AED 4,000,000) |
| Taxable income | AED 6,000,000 |
| Tax: 0% on first AED 375,000 | AED 0 |
| Tax: 9% on AED 5,625,000 | AED 506,250 |
Sources and legal basis
Legislation and decisions2
- Federal Decree-Law No. 47 of 2022
- Ministerial Decision No. 229 of 2025
Authorities, systems and registers3
- UAE Federal Tax Authority
- UAE Ministry of Finance
- EmaraTax
Terms used1
- Dubai Municipality
- Corporate Tax – Federal Tax AuthorityUAE Federal Tax Authority
- Corporate Tax – Ministry of FinanceUAE Ministry of Finance
Rates, thresholds and deadlines change. Every figure above is linked to the authority that publishes it — if the two ever disagree, the authority is right and this page is out of date. Tell us and we will fix it.
Frequently asked questions
Are liquidated damages deductible?
Yes. Contractual liquidated damages for delay are a cost of the contract, reducing revenue or deducted as incurred following the accounts. They are commercial consequences, not regulatory fines, so Article 33 does not block them. Keep the client's deduction certificate with the contract clause.
What if we joint-venture the project with another contractor?
An unincorporated joint venture is generally tax-transparent, with each venturer taxed on its share of the profit. The JV agreement's profit split and the accounting allocation decide each party's computation. Keep the JV accounts as carefully as your own.
Does a contractor register before winning its first project?
Yes, if it is a juridical person carrying on business. Registration under Article 51 follows the business activity, not the first contract; a contractor tendering with staff and overheads is already within scope. Early registration also preserves tender-stage losses for carry-forward under Article 37.
When is the contractor's tax return due?
Within nine months of the end of the tax period (Articles 53(1) and 48 of Federal Decree-Law No. 47 of 2022), with any tax payable by the same date. Stage-of-completion certifications and subcontractor accruals must be finalised before the return, because they decide the period's profit. Late filing attracts administrative penalties.